Notre Dame: A wake-up call for the Palace of Westminster?

images.001download.001News reports suggest that the long-delayed Restoration and Renewal of the Palace of Westminster will be accelerated in response to the devastating fire at Notre Dame. Alexandra Meakin and Alexandra Anderson discuss why progress has been slow and the need for action to address the fire risk in Parliament.

The devastation at Notre Dame in April 2019 is a stark reminder of the dangerously high fire risk facing the Palace of Westminster. The home of the UK Parliament has been very lucky to escape its own catastrophe, with ‘sixty-six incidents that had the potential to cause a serious fire’ since 2008. Wardens have been patrolling the Palace 24 hours a day in order to mitigate the major fire risks and to address the inadequate fire alarm systems. Part of the problem is due to the very structure of the building, as after the devastating fire which destroyed the old building in 1834, the rebuilt Palace included an extensive ventilation system that ‘unintentionally create[d] ideal conditions for fire and smoke to spread through the building’.

Speaking in the House of Commons on Thursday 25 April, the Labour MP Chris Bryant highlighted the Notre Dame fire in order to call attention to the urgent need for the Restoration and Renewal of the Palace of Westminster (R&R) to be carried forward as soon as possible. Bryant, a long-running campaigner for rebuilding the Palace of Westminster (and potential candidate for Speaker should a vacancy arise during the current parliament), noted that while the fire in Paris had caused unimaginable destruction, there had been no fatalities. It would, he warned, be very different if such a fire was to take hold in the Palace of Westminster, where 9,000 people work every day and one million people visit each year.

The fire risk in Westminster has been well-known for years. A 2012 report set out the need for the major refurbishment programme in order to address the fire and flooding risk caused by the buildings’ dilapidated infrastructure that is decades past its expected lifespan. Four years later, the Joint Committee on the Palace of Westminster emphasised the growing risk to the building, warning that:

‘there is a substantial and growing risk of either a single, catastrophic event, such as a major fire, or a succession of incremental failures in essential systems which would lead to Parliament no longer being able to occupy the Palace.’

The Committee called for action without further delay, to ‘restore and renew this historic building for the future, and to ensure that the Palace of Westminster is preserved for future generations’. Continue reading

Leaving the European Union, leaving the Palace of Westminster: Brexit and the Restoration and Renewal Programme

download

A year after the House of Lords backed a major refurbishment of the Palace of Westminster, Alexandra Meakin discusses the relationship between the UK’s upcoming departure from the EU and the plans for MPs and peers to temporarily move out of their current home.

Anna Soubry: ‘We have to grasp this, do the right thing, and – I cannot believe I am going to say this – but in this instance, in supporting amendment (b), absolutely everybody vote leave.’

Over the past few months parliamentary proceedings have taken centre stage in our nation’s consciousness. The legislative and political machinations surrounding the UK’s planned exit from the European Union have turned the Palace of Westminster into a theatre offering endless drama and occasional farce. Indeed, the wider area around the Palace has been absorbed into the set: the pro and anti-Brexit protests in Parliament Square; the broadcasters’ gazebo village on College Green; and even the steps outside St Stephen’s entrance, which hosted an impromptu press conference. The audience following every scene, however, couldn’t fail to observe the scaffolding covering the set, the external sign of a dilapidated building, where the infrastructure is decades past its expected lifespan. Alongside the preparations for departing the EU, MPs and peers are also planning for a further departure: leaving the Palace of Westminster to enable a major refurbishment programme.

After decades of neglect, the scale of the problem inside Parliament was outlined in a 2012 report, which noted ‘if the Palace were not a listed building of the highest heritage value, its owners would probably be advised to demolish and rebuild’. On receipt of the report the governing bodies in the Commons and Lords agreed that ‘doing nothing was not an option’. They ruled out the construction of a new parliamentary building, and committed instead to further analysis of the options for repairs, and specifically whether the work could be carried out while both Houses continued to sit in the Palace. Continue reading